DETAIL SUBMISSION
School CodeNBA0034
School NameSEKOLAH KEBANGSAAN (FELDA) PASOH 4
NameHAFIZUL SUKRI BIN MAMAT YUSOFF
CompanyMEGAFOX RESOURCES
Emailmfcomm22@gmail.com
Phone013-7373281
SUPPORTING DOCUMENTS
Work Program (WP)WORK-PROGRAM-SK-FELDA-PASOH-4.pdf
Work Program (WP) StatusUploaded
WP ApprovalApprove
Preliminary BOQ
  • PRELIMINARY-BOQ-SK-FELDA-PASOH-4.pdf
  • PRELIMINARY-BOQ-SK-FELDA-PASOH-4-100625.pdf
Preliminary BOQ StatusUploaded
BOQ ApprovalApprove
Insurance 1Policy-Schedule-CAR-Megafox-Resources_Infra-Works-for-Global-Technological-Support-Sdn-Bhd.pdf
Insurance 1 StatusUploaded
Insurance 1 ApprovalApprove
Insurance 2Policy-Schedule-WC-Megafox-Resources_Infra-Works-for-Global-Technological-Support-Sdn-Bhd.pdf
Insurance 2 StatusUploaded
Insurance 2 ApprovalApprove
Notis Mula Kerja (NMK)NOTIS-MULA-KERJA-SK-PASOH-4.pdf
Notis Mula Keja (NMK) StatusUploaded
NMK ApprovalApprove
Notis Mula Kerja (NMK) Date06/02/2025
KACP PTWPTW-SK-FELDA-PASOH-4_APPROVED.pdf
KACP PTW StatusUploaded
PTW ApprovalApprove
Final Submission StatusApprove
© 2024 Apex Communications Sdn Bhd 198901010174 (187475-V) | All Rights Reserved
    • Pre-Installation
      • FDP Requisition Form
      • Delivery Note (DN) Submission
      • Material Requisition Form Submission
      • Supporting Documents Submission
      • QR Sticker Request
      • Material Transfer Form
    • Post-installation
      • Site Completion Evidences Submission
      • Inspection Rejection Note (IRN)
      • HOD (60% Progress Claim)
    • Post KKOM Veriffication
      • HOD (10% Progress Claim)
    • Procurement
      • Material
        • 1st Progress Payment 90%
        • 2nd Progress Payment 10%
      • Deployment
        • 1st Progress Payment 20%
        • 2nd Progress Payment 60%
        • 3rd Progress Payment 10%
        • Final Payment 10%