SUPPORTING DOCUMENTS
Work Program (WP)002-WORK-PROGRAM-ABA6043-SK-SUNGAI-BAYOR.pdf
Work Program (WP) StatusUploaded
WP ApprovalApprove
Preliminary BOQ
  • 004-Prelim-BOQ-ABA6043-SK-SUNGAI-BAYOR-rev01.pdf
  • 004-Prelim-BOQ-ABA6043-SK-SUNGAI-BAYOR-rev02.pdf
Preliminary BOQ StatusUploaded
BOQ ApprovalApprove
Insurance 1
  • 003-FIBRE-OPTIC-HDD-CAR-WC-Quotation.pdf
  • POP-2-Endorsement-C.A.R-PCOM-_25EKL0000581-00-001-17.04.2025-to-30.10.2026CAR-Policy.pdf
Insurance 1 StatusUploaded
Insurance 1 ApprovalApprove
Insurance 2
  • 003-FIBRE-OPTIC-HDD-CAR-WC-Quotation1.pdf
  • POP-2-Endorsement-WC-Extra-5-PCOM-25WKL0000618-00-002-17.04.2025-to-30.10.2026-WC-Policy.pdf
Insurance 2 StatusUploaded
Insurance 2 ApprovalApprove
Notis Mula Kerja (NMK)
  • 001-NOTIS-MULA-KERJA-ABA6043-SK-SUNGAI-BAYOR.docx
  • 001-NOTIS-MULA-KERJA-ABA6043-SK-SUNGAI-BAYOR.pdf
Notis Mula Keja (NMK) StatusUploaded
NMK ApprovalApprove
Notis Mula Kerja (NMK) Date06/23/2025
KACP PTW006-PTW-ABA6043-SK-SUNGAI-BAYOR_approved.pdf
KACP PTW StatusUploaded
PTW ApprovalApprove
OthersProforma-INV_002.pdf
Final Submission StatusPending Approval
© 2024 Apex Communications Sdn Bhd 198901010174 (187475-V) | All Rights Reserved
    • Pre-Installation
      • FDP Requisition Form
      • Delivery Note (DN) Submission
      • Material Requisition Form Submission
      • Supporting Documents Submission
      • QR Sticker Request
      • Material Transfer Form
    • Post-installation
      • Site Completion Evidences Submission
      • Inspection Rejection Note (IRN)
      • HOD (60% Progress Claim)
    • Post KKOM Veriffication
      • HOD (10% Progress Claim)
    • Procurement
      • Material
        • 1st Progress Payment 90%
        • 2nd Progress Payment 10%
      • Deployment
        • 1st Progress Payment 20%
        • 2nd Progress Payment 60%
        • 3rd Progress Payment 10%
        • Final Payment 10%